Description
Reconfiguration of a 25 kV distribution line
As part of a provincial maintenance contract delivered through a joint venture, we modernized a 25 kV line over nearly 30 km, converting it from single-circuit to double-circuit configuration. This two-year project, which required multiple outages, mobilized our teams for the framing of new structures, installation and replacement of conductors, dismantling of existing infrastructure, and strategic traffic management. In the photo, our crews are pulling the new conductors, a key phase of the project.